Contributed by Liz O'Sullivan On a recent project of mine, the lack of a submittal for the contractor’s proposed solution to an unexpected situation caused a problem. The contractor didn’t think that a submittal was required by the contract documents, and the architect didn’t realize that a submittal was required by the contract documents. The contractor could have saved himself some money and time, and could have saved the architect and the owner some time, if the contractor had just prepared a submittal for the architect’s review before proceeding with the work. (Oh, yes, some freshly-installed flooring underlayment had to be removed before the project could proceed. THAT was a waste of time and money.)
If something is added to a project, because of an unforeseen condition, everyone (architect, owner, contractor) often acts as if it’s the first time this sort of thing has ever happened. It’s not. Unexpected things happen all the time on construction projects, and that’s why we have standard processes to deal with them. Anything that wasn’t originally in the project, but is part of the project now, is in the contract as the result of either a change order or a minor change to the contract. Whether it’s a moisture mitigation treatment for an existing slab, or a whole new roof assembly, whether it was initiated by an owner as a late addition to a project, or it was initiated by the contractor as a solution to an unexpected condition, or initiated as a substitution request because of a sudden product unavailability, it ends up in the contract as the direct result of a change order or a minor change (such as the type authorized by an ASI, Architect’s Supplemental Instructions). Even when the change results in no added cost to the owner, and even when its purpose is solely to repair a mistake made by the contractor, it’s a change, and it should be documented (and submitted on). Architects and specifiers can make sure that the contract documents require submittals for things that weren’t originally in the project. Requiring submittals for items added to the project during construction is a good idea. In fact, requiring submittals for items added to the project during construction may be even more important than requiring submittals for things that were originally part of the design, since the new element wasn’t originally thought through along with the rest of the design. The contractor’s preparation of the submittal, and the architect’s review of the submittal, act as a double-check mechanism to help make sure that the added item will be appropriate.
1 Comment
Contributed by Eric D. Lussier In a few short days, Cherise and I will once again jump on a plane and converge on a new locale to spread the Let’s Fix Construction message. A new conference, and with that, a new audience, awaits in Anaheim at the AEC Next Technology Expo & Conference to hear a little about the who and a little more about the why behind what we’re doing.
With LFC being founded steeply in our Construction Specifications Institute roots and beliefs, much of the message of LFC and CSI remains in our closed loop circles if we do not do our part in getting in touch with the onlookers and informing new individuals about the who, the what and the why in 2019 and beyond. These continued opportunities will never cease to amaze me. Cherise and I go into each one grateful for the chance to spread the message of Let’s Fix Construction and to perhaps spark an AHA! moment for even one of our attendees. For I truly believe that it only takes one person to walk away from one of our workshops to know that we’ve done our part. One person to tell us after attendance that they could feel our passion for what we’re doing. One person to say that they got more out of one session than a year of box lunches. And Cherise and I are just two voices for Let’s Fix Construction. With our Speed Mentoring session in Anaheim, Let’s Fix Construction becomes dozens of voices, encompassing hundreds of years of construction experience, which will be conveyed to dozens more new receptors of our message and mission. The AEC industry is undergoing monumental change and culture shifts and the next twenty years are vital to not only our future, but our children’s, grandchildren’s and great grandchildren's future. It’s important for all of us to continue to spread our knowledge and experience, and personally for Cherise and me, our mission and our passion that we deploy within Let’s Fix Construction. You may not have the opportunity to join us in Anaheim at AEC Next, but there will be other chances. We’re always listening and open for new formats to offer creative solutions, separate myths from facts and erase misconceptions about the architecture, engineering and construction (AEC) industry. Contributed by Mike Lapre When surety companies are asked to provide bonding for individuals or companies, the level of credit which is involved can generally be determined by a fairly universal formula which is observed by the surety industry. That formula is based on what is known as the three C's, and these are factors which will serve as a strong guideline for determining just how much credit can safely be extended to any bonding applicant. Those three C's are described below, so that if you have a fairly clear idea of how your company rates in each of these three areas, you should also have a fairly clear idea of just what level of credit you're eligible for.
Character Any underwriter who is trying to evaluate an applicant's character will take into account their personal credit history, their business credit history, their track record for paying bills, reputation in the community, any public liens or judgments, and their management experience. Any of these areas which are found to be weak or questionable will definitely have an impact on the underwriter's decision, although it probably would not disqualify an individual from becoming bonded. There are also ways in which you can improve on these areas, so that you're more likely to be bonded for the amount you want. Obviously one of these areas is to make sure that you pay your bills on time consistently, and that you catch up on any outstanding old bills you may have. It's a good idea to have lines of credit available to you, but it would be better if they are not used often. It's always good to keep an updated resume on hand, in case it's needed for consultation by a bonding agent. You should be able to explain any negative lines or mistakes on your credit history, or any past-due items which appear there, whether or not you caused them. You should always be as honest as possible with your bonding agent, and consult with them whenever there are any major financial events which have occurred to your business. By being forthright on all these issues, you'll have a much better chance of achieving the level of bonding that you are hoping for. Contributed by Michael Chambers Recently, a national trade association contacted education presenters to provide them with the evaluation results for their programs. This is a large association with a very strong focus on technology and its applications in business, education, worship, and industry. Their national convention offers hundreds of hours of educational opportunities for the attendees.
In general the education programs were very well received and evaluated. Attendees rated 90% of the programs at 4 (out of 5) or above for “overall quality and interest”. However, it is interesting to note that the same attendees indicated that less than 10% of the programs were rated 4 or above for “applicability to daily practice”. In other words, attendees thought the programs were very interesting but came away with nothing they could use in day-to-day practice. In my experience this is true of most of the continuing education that I receive from product manufacturers’ box lunches, AIA continuing education programs, and CSI Chapter presentations. The majority of them are interesting and provide USEFUL information but rarely do they ever provide USABLE information. The concept here is much like searching the web on Google™ or Yahoo™, you end up with hundreds of USEFUL items but only a tiny fraction are truly USABLE. If continuing education is to have a positive impact on the construction industry, developers and presenters are going to have to put real, applicable content into the programs. To effectively use continuing education as a marketing and communication tool, the content presented must be directly applicable to the day-to-day operations of the audience. Information about a product’s features and benefits is quite useful, as marketing hype, but it is rarely usable since design professionals need industry information, technical data, design guidelines, and details to effectively integrate a product or system into a building project. In any type of presentation to design professionals, the focus must be on providing USABLE rather than USEFUL information. I guaranty it will transform your relationships with design professionals and enhance your professional credibility. It is critical to provide continuing education information on how to specify the product and to provide examples and details of how to appropriately incorporate the product into the drawings. I am constantly amazed how few educational presentations even discuss specifying and even less, how to detail and coordinate the drawings. The best and most effective presentations are extremely simple, no PowerPoint™ or flim flam, just product installation examples, guide specifications, and example construction drawings of successful installations. That is truly USABLE information and HIGHLY EFFECTIVE continuing education. (Editor's Note: Michael D. Chambers, FCSI, FAIA, CCS is Associate Vice President and Senior Project Specifier for HGA and is responsible for the specifications in the four California offices and is principal of MCA Specifications. Michael also sits on the CONSTRUCT Education Advisory Council with Let's Fix Construction Co-Founders, Cherise Lakeside and Eric D. Lussier. NEW FOR CONSTRUCT IN 2019! The NEW Product Rep University Program has been designed to meet the needs of Manufacturer's Representatives of Architectural Building Products, as integral members of the project team. The program features a full day of education (6 sessions) to help you stay up to date on current trends in the industry, and refine your interactions and relationships with design professionals. Get additional details on the Product Rep University here: www.constructshow.com/PRU Download a Product Rep University flyer here. CONSTRUCT will be held October 9 - 11, 2019 at the Gaylord National Resort & Convention Center in National Harbor, MD. Read more on CONSTRUCT here. ) Contributed by Eric D. Lussier I sat through a pre-construction meeting via conference call today to go over the ins and outs of our upcoming flooring installation. This project will be a combination of a renovated facility, with a new addition being constructed. We have a scope within each section, installing two dance floors in the renovated side and installing 5,000 square feet of gym flooring in the new construction.
After we were asked to review our approximate duration on site to complete our work, we were addressed with the question "how long after the slab pour can you be installing your floor? Is two weeks enough?" At first, I thought I didn't hear the general contractor right, so I didn't put much emphasis on it. But then it was posed again. The project was behind schedule, they still wanted to be completed in May and they wanted to know how soon after the slab was poured could we be in there installing the floor. First, let me just say that we are supposed to utilize an on-slab vapor barrier as part of our synthetic gym flooring system that allows us to install up to 100% relative humidity in the concrete slab. But, but, but...two weeks after the pour? Were we really being asked that? We're going to be putting a non-breathing system on essentially a brand-new slab and then expect it to behave in a predictable manor? Secondly, how legitimate is this actual request? All other trade work needs to be done before the flooring actually goes in. Not only does that include the HVAC system, lighting and basketball hoops, among others, but they'll all be done within those two weeks? For the record, our flooring's installation instructions ask that "the concrete subfloor will be cured for a minimum of at least sixty (60) days.” That would put us well beyond the proposed opening date for the school. Fortunately, we can offer a two-part epoxy moisture mitigation system, which can be utilized with the only parameters being “Newly prepared concrete must be cured for 7 days”. We addressed our timelines and concerns and wrapped up our conference call after the Owner stated his position to the General Contractor on the importance of the schedule being met. He stated that our call should have been held months ago to state that the flooring couldn't go in during such a short window after placement. But was it really necessary to tell them this months ago? Is it not common knowledge what a typical new construction duration is? |